Saturday, April 16, 2016

April 16, 2016

Construction is going well. We still have issues that need to be resolved but things are moving. We are working to get the front grassy area free of weeds because we plan to have our May Day program there for this year only. That is the only area that is large enough to accommodate the whole school. Roofers are starting to lay the insulation at the outdoor play court, and the upstairs of the library media/student center is almost complete. We are waiting for the fire inspection so we can occupy J5, the special education classroom. There is evidence of progress!

It took 8 workers to get this logo installed.
Looking at the covered play court from the back of the school 
The insulation is ready to be laid on top of the metal pan decks.  

The soaring eagle logo - there is one outside the library and one in the covered play court by the stage. I really like how it turned out - very classy!

Sunday, April 3, 2016

April 3, 2016

Well, it's April, and we get closer and closer to the completion of this project. Let's check out what is happening with the construction this past week.

Completing the structural steel beams for the covered play court roof
Getting ready to pour the concrete for the covered walkway on the side of the Library Media/
Student Center
Laying the rubber floor tiles on the second floor
Installing the last window on the second floor of the Student Center
New, lighter stackable chairs in the office conference room - they are wonderful!
Getting the covered walkway ready for the concrete pour in front of the Student Center
I think the pour will be in the next week or so.
Pouring the concrete for the covered walkway last Friday 
Most of the metal pan deck has been laid in place for the covered play court.
Next up - the insulation.