Saturday, February 27, 2016

February 27, 2016

Recent photos of our construction project:
Walkways are being completed in phases. This is on the side of the new building; when completed, there will be a covered walkway to the cafeteria. 
On the same day the workers poured cement for the walkway in the photo above, they also poured this walkway near the administration building.
Facing the covered play court from the side near the cafeteria 
The back of the building 
The side of the building from the back of the school 
The day after the cement was poured, workers were using this machine. I think they were "roughing" the surface so it would be safer for our students, staff, and families.



Tuesday, February 16, 2016

February 16, 2016

Here's what been happening with the construction project!

Students are playing at recess while work goes on in the background. Workers were pouring cement for the columns. Those machines continue to amaze me! 
Workers were pouring the cement for the poles for the covered walkway adjacent to the administration building.
The covered walkway will eventually extend to the cafeteria. 
Today, they put in the supports for the walkway. The cement will be poured later this week.  
Inside the library media/student center, workers are pulling wires for connectivity. Frankly, I still don't know how they know how they pull those wires through those small pipes and then know what goes where. Good thing I'm not an electrician!
The light fixtures were installed in the library media/student center. Next, the ceilings will be installed.

Sunday, February 7, 2016

February 7, 2016

Time sure is flying! Here it is, Super Bowl Sunday already which means it's the month of February.

The work on our library media/student center and the covered play court continues. Here are a few photos (sorry, not too many this time).

This is the ceiling in one part of the library. The silver cylinders are for the air conditioning; they will be covered unlike the white ones that are in the library area.
These are the shelves in the Media Coordinator's office. We're not sure who will be using this room. It'll either be Mrs. Cummings or Mrs. Armstrong.
This is the ramp in front of the new special education classroom. It goes from J-building to the covered play court. 
The front of the covered play court has an area for a stage where we can have school-wide assemblies. We will have an eagle logo as a backdrop. There's still more work to do on the columns before workers will start installing the roof.