I didn't realize that it's been two weeks since I updated this blog. I apologize for missing last week.
Next week, we'll be temporarily moving P13 to G1 and P17 to H2 so that the contractors can complete the sidewalk to join the new classroom building and A-building. This should be temporary, and hopefully, the classes will be able to move by spring break. In the meantime, Mr. Merriam will go to the classes to do drama, and the Instructional Coaches have moved to other classrooms so the students can have a classroom.
More happenings with our project:
|
The grass is starting to grow! The landscaper said 6-8 weeks; it's been 2 weeks now. Let's see how long it'll take. |
|
The contractor's office is now right in front of the main office. They're slowly moving the staging area to the back of the school, but first, they have to build a new gate so the workers can get in and out. |
|
The dining pavilion furniture was installed yesterday and today! 6 round tables, 2 with handicapped accessibility, 7-8 to a table. Landscapers will be planting grass around the area, probably during spring break. |
|
The whole side area by Waianae Avenue will be blocked off next week to start work on the covered playcourt. PE will be moved to the back of the school, and recess times will have to be adjusted now that the space is limited. |
|
In a couple of weeks, they'll be pouring more of the SOG. I think that may be the last concrete pour for the slab on grade. |