This past week, we were able to tour the interior of the library media/student center. The metal pan deck for the roof is just about completed (the weather delayed the completion), and the metal frames for the interior of the building are being installed. Air conditioning ducts are in place in the library portion of the building.
Work continues on classroom J5 as well as the covered play court.
The roofers are working on installing the metal pan decks for the roof of the library media/student center. Once this is done, they will install several layers of insulation. |
This is what the metal roofs look like from inside the building. |
Those cylindrical tubes are for the air conditioning in the library. |
This is the hallway in the student center. The speech pathologists will work in the large room on the right. On the left are several office spaces for the counselors and Behavior Health Therapist. |
Workers are checking to make sure the metal pan decks were installed correctly. |
We walked through this room as well. The electricians were still installing the outlets, and there is still much work to be done. Hopefully, we can use this classroom during the school yea. |
One sidewalk was already poured for the outdoor play court, but there is still much more that has to be done on this phase of the project. |
No comments:
Post a Comment