Friday, January 3, 2014

January 3, 2014

The heavy rains the past couple of days ruined our plans for the week, but if the weather is nice this weekend, we should be back on track. The trench in the back of the school is completed  and ready for the data lines to be connected closer to the summer. (below left)  The trench in the front of the school is almost done, but workers could not complete the final step of pouring cement.  The classroom building is progressing; one set of footings is done and workers will be pouring the next set of footings sometime in the coming week, weather permitting.  (below right) Sometime in the next couple of weeks, workers will put in the steel beams for the roofing on our administration building.

Teachers return to school on Monday, and students return on Wednesday.  Happy New Year, everyone!