Thursday, June 26, 2014

June 25, 2014

What's happening this week:

  • Buildings B, C, D, E, and G exterior and interior painting 
  • Re-roofing and installing gutters on buildings E and G 
  • Begin installation of the flooring in the administration building
  • Start up and switch over to the new electrical system 
  • Pulling wires for cable, data, and phone systems
  • Install lighting in the administration building
  • Pour concrete for the walkway in front of the administration building
  • Pour concrete for the stairway in the classroom building
  • Begin work on the dining pavilion
These are the things I can visibly see; I'm sure there are many more projects underway!

I'll be at a conference and won't return until next Thursday.  I'm sure there will be more changes  at that time.  Until then, here are a few photos to document what's happening on our project.

The new walkway in front of the administration building.  There's a small section that still needs to be completed; you can see the workers in the back working on the framing for the next concrete pour.

I am still amazed at how this machine can pump out concrete; at the time this photo was taken, they were working on the stairs in the classroom building.

Since school is not in session now, they've taken down the black tarp so we can see the progress of the classroom building.  They're working on the second floor.

The roofing work is taking more time than anticipated, so the roofers will begin coming in on weekends, too.  I'm used to smelling tar when they're fixing roofs, but this process doesn't use tar (thankfully).