It's July 11, 2014, and school begins for our students in just 3 short weeks. All of the workers continue to work long hours and on weekends to finish their job. We appreciate their diligence.
 |
These are the acoustical clouds in the administration building which are designed to reduce noise level and add a contemporary look to our office. |
 |
G4 has been transformed into a bright and cheery temporary library for students to peruse and borrow books. Thanks, Mrs. Huszar, for your hard work in getting this room ready! |
 |
The second story of the classroom building is coming along nicely. We are hopeful that the December deadline will be met. |
 |
Painters are finishing the doors on the renovated classrooms. The color is a dark turquoise blue to match the building exterior and the floor tiles. |
 |
The front of the administration building will be mostly glass. Workers have been installing the frames this week. |
 |
It's Friday, and the frames are all done. They will install the colored glass next week. I can't wait to see how it looks! |