This was a productive week especially for the masons! We had a big concrete pour on Tuesday, and the bricklaying started the next day. Look at how much was accomplished by the end of the week!
|
The SOG was ready for the concrete pour on Tuesday, February 24. |
|
Many hands make light work! |
|
All done! |
|
Starting on the walls for the library media/student center |
|
There was also a concrete pour for the sidewalk that connects the new classroom building to Building A. Students will now have access to P11, P13, and P17 once again. |
|
Masons are working on the Student Center part of the new building which will house the Student Services Coordinator, counselors, speech pathologists, behavioral health therapist, our instructional coaches, and the Tripler SMHT program. There will be rooms for meetings and for testing, too. |
No comments:
Post a Comment