It's Spring Break, and the workers are hard at work! Next week, they will start laying the floor tiles upstairs in the Student Center and the Media Center. Those rooms will be almost done after the floors are done.

Here are some photos from last week:

The structural steel beams are being installed on the covered play court.
Another view of the covered play court
This is the hallway of the Student Center. Notice the screens that filter some of the light on the top floor.
The ceiling and lights are installed in most of the second floor rooms.
The structural beams will be placed next week. 
These structural beams had to be welded together. Next week, there will be a huge crane lifting these beams into place. Workers will then guide the beams into the notches. 