Completing the structural steel beams for the covered play court roof |
Getting ready to pour the concrete for the covered walkway on the side of the Library Media/ Student Center |
Laying the rubber floor tiles on the second floor |
Installing the last window on the second floor of the Student Center |
New, lighter stackable chairs in the office conference room - they are wonderful! |
Getting the covered walkway ready for the concrete pour in front of the Student Center I think the pour will be in the next week or so. |
Pouring the concrete for the covered walkway last Friday |
Most of the metal pan deck has been laid in place for the covered play court. Next up - the insulation. |
No comments:
Post a Comment