It's summer break, so I'm able to go out to check on the progress and take photos.  I'm wondering if I'll be able to once the 12' barriers go up.  I need to check with the project manager.

Things are starting to move with the project.  We took a walk around the area today, and I was surprised at the size of the buildings when completed!  There won't be much of a play area after the administration and classroom buildings are done..  Fortunately, the area in the back of the school should be larger once the portables are removed.

Here are a few photos I took today as well as some comments.
A storage container was brought in so the contractors
can store their tools and supplies.  Even if we are on
a military base, they still need to lock up their supplies
and materials in the evenings and on weekends.
Yesterday, the workers were digging the area to make the
entrance for the construction vehicles.  Today,
it's done! 


T
Dirt piles are starting to accumulate on campus.  This pile is from the  entrance area for  trucks and other vehicles.  Some of the dirt is really rich-looking, and we think we should add it to our gardens around campus.
Workers are digging the trenches for the electrical lines
for P12 and P13.  
Notice what's missing from P13?  The stairs!  The
contractor will be putting in new stairs to replace
the ones which in need of repairs.  We hope to
have the portables moved by July 25 (sooner,
if possible).





Wow!  These are the materials to build the 12' barriers to keep us out of the construction area.   The barriers are going up soon!  A-building will get pretty hot since they won't be able to open their windows.  